Snapshot:
Fulton Bank is a community-focused, mid-sized financial institution headquartered in Lancaster, Pennsylvania. At the time of the interview, its Internal Audit team planned approximately 115 audits and projects each year, representing about 36,000 hours of work across 30 people.
Fulton Bank’s Internal Audit team enters each year with almost no excess capacity. Heather Hirschmann, Director of Audit Professional Practices at Fulton Bank, explains, “Our audit plan is approximately 36,000 hours, and our people’s availability is 36,000 hours, so there’s not a lot of open time. And as audits go over, which naturally they will do, there has to be that flexibility for me to be able to push things or add a day here, take a day here, put somebody totally new on.”
The team also needed a stronger scheduling approach after moving to a newer version of its long-standing audit management platform. Its replacement scheduling capability did not provide the level of planning and visibility the team had relied on.
Leaders needed a way to answer critical questions such as:
Weekly oversight was also highly manual. Every Monday, seven to eight senior team members each spent one to two hours reconciling actual time with scheduled time by person and by project. Before leaders could make a decision, the team first had to collect information from multiple reports and assemble it in a common template.
The constraint was not simply the amount of work. It was the narrow margin between demand and available capacity. When the audit plan and the team’s expected availability both equal approximately 36,000 hours, there is little room to absorb an overrun, a staffing change or an unplanned project without affecting something else.
“I need to know that last week you should have worked 20 hours on my audit. On Monday morning, you only put 15 hours. So what happened to the other five?” says Hirschmann.
The team needed a current, shared view of the plan so it could identify variances before they became delivery problems and make explicit tradeoffs when planned work exceeded available capacity.
Fulton Bank implemented Tempus Resource alongside their existing TeamMate solution to create a connected planning and reporting approach. Actual time from TeamMate feeds into Tempus Resource, while a tailored Insight+ dashboard in Tempus brings together daily schedules, project schedules, annual workloads, availability, planned time off, and comparisons of actual versus scheduled hours.
The objective was not simply to replace a scheduling function in their existing solution. The Internal Audit team needed a faster way to understand whether the plan was unfolding as expected and what adjustments were required when reality diverged from the schedule. By combining scheduling, utilization, capacity, and actual time data in a single view, leaders can quickly identify variances, understand downstream impacts, and make informed decisions about staffing, scheduling, and audit delivery.
“Instead of spending an hour or two for seven people every Monday to reconcile time, it’s done, and they can just take a look at it and let me know what adjustments need to be made based on that,” says Hirschmann.
“Instead of spending an hour or two for seven people every Monday to reconcile time, it’s done, and they can just take a look at it and let me know what adjustments need to be made based on that.”
– Heather Hirschmann, Director of Audit Professional Practices at Fulton Bank
This shift allowed the team to spend less time gathering and validating information and more time acting on it. Leaders can now identify where schedules need to be adjusted, determine whether audits require additional support, and evaluate the impact of changing priorities before those issues affect delivery
A process that previously required seven to eight senior employees to spend one to two hours every Monday is now automated. Rather than gathering and reconciling information, senior team members can review the completed comparison and focus on the schedule adjustments it reveals.
The team can compare scheduled and actual work at the individual and audit level. If someone was scheduled to spend 20 hours on an audit but recorded only 15, leaders can see the five-hour gap, understand what prevented the planned work and determine where those hours must move. That insight helps the team respond while there is still time to protect future deliverables.
Capacity planning is now grounded in both planned demand and historical availability. If the audit plan rises to 40,000 hours while available capacity remains at 36,000, leadership can make the tradeoff explicit by modeling changes and scenario planning – remove work from the plan, add staff, use an intern or bring in co-sourcing support.
Fulton Bank can account for different working patterns by level and by person, including managers, senior auditors and part-time employees. Leaders can compare annual utilization and adjust assignments so one person is not carrying a heavier load than another without a clear reason.
When a special project is added or an audit must move from one month to another, the team can see available capacity, replace auditors or shift an entire audit. This gives leaders a more practical way to accommodate change without rebuilding the plan from fragmented reports.
Fulton Bank now manages its audit plan as a living operating commitment rather than a static annual schedule. Leaders have a clearer view of whether work is progressing as planned, whether capacity assumptions remain realistic and what must change when demand and availability no longer align.
The most important shift is from discovering a problem after it affects delivery to seeing the variance early enough to act. The team can spend less time compiling information and more time deciding how to protect the audit plan, balance workloads and meet a critical annual commitment. Schedule time with our audit planning experts now.